[02/02/23] Standard Delivery on ALL products/orders

Please know that due to supply chain challenges, material, and labor shortages, ALL products/orders are to be shipped standard delivery until further notice. Lead times and ship dates are estimated only and can change at any time.


[02/28/23] - Partial Shipments

If some of the products on your order have a longer lead time and you would for products with a shorter lead time to ship first, please follow the steps below to opt for partial shipments.


  1. Click the 'projects' tab, found under 'project management'
  2. Check the box next to the order you would like to split
  3. Select 'Order' from the options at the top of the page
  4. Find 'Allow partial shipments?' at the bottom of this page and select 'yes' from the drop-down
  5. Click 'Place Order'

PLEASE NOTE: This gives S&P USA permission to ship some products earlier if other products on the same order have longer lead times. This may also result in multiple invoices sent for the same order.


[12/15/22] - 2023 ERV Freight Policy

Effective January 3, 2023, S&P USA Ventilation Systems will implement changes to ERV/TR Freight rates.

2023 ERV/TR Freight rates in various regions are as follows:

  • 1% of list price - MN, WI
  • 1.5% of list price - IL
  • 2.5% of list price - IA, IN, KS, KY, MI, MO, NE, OH
  • 3% of list price - AL, AR, GA, LA, MS, NC, ND, OK, SC, SD, TN, TX, WV
  • 3.5% of list price - CT, DE, MA, MD, ME, NH, NJ, NY, PA, RI, VA, VT
  • 4% of list price - AZ, CA, CO, ID, MT, NM, NV, UT, WY
  • 4.5% of list price - FL, OR, WA
  • Surcharges will remain but are subject to change. This charge is included in the total ERV Freight Cost.

Please see ERV/TR policy here.


Product Lead Times - as of 3/06/23

Please know that Lead Times are subject to change at any time.

Model Number Lead Time
LCE/LCS/LE/LS, DFE/DFS, DDE/DDS, TDB, TDD,
UBB/UBS/UBX/UBRD, HRSB/HRSD, HREB-C/HREB-P/HRED-C,
UBSRD/ UBSRD-P, SMXD/SMXD-K, CTB, TUB
28 Weeks
reFresh - RF 8 Weeks
CM, CFD, SDB/STXB, KSFV, CSF, RFC 18 Weeks
SQD/ eSQD, SQB 20 Weeks
STXD/STXDe (See EC Motor lead time exception below) 13 Weeks
SDBD/ SDBDe, LPD, CWD, RCXII, RLX,
GED/eGED, ARE (See EC Motor lead time exception below)
10 Weeks
Jet Fans - IFFT/ IFFTe, TJFU, IFAB/IFEB 8 Weeks
Individual Parts/Fab - Please email
custserv.jax@solerpalau.com for
details.
3-5 Weeks

TR/ERV Lead Times

All TR/ERV orders require a custom freight quote. These products are excluded from S&P USA's Free Freight Allowed (FFA) Program. See lead times below. Lead Times are specific for 1 unit only.

Due to supply chain issues, the TRCe1200-230 is not available at this time

SIZE WKS
TRC500-TRC800 10
TRC-1200, TRC1600, CA 18
   
RES (< 1 pallet) 1-2 weeks
RES (2-3 pallets) 4-5 weeks
RES (> 3 pallets) 6-8 weeks

The commercial unit table assumes a single unit. Orders of custom units / multiple units / larger quantities may increase lead times from above.


EC Motor ID 1310.11NM.17, 1/3 HP Lead Time

Please note that the EC Motor ID 1310.11NM.17 currently has a lead time of 120 days. This is due to supplier challenges and will affect models for the SDBDe, STXDe, STXDeRHUL, STXDeW, and STXDeWRHUL series. We apologize for the inconvenience.


Ecowatt-Drive (VFDs)

The Ecowatt-Drive (VFDs) speed controls are currently unavailable due to supplier shortage. If you select any VFD speed control, your order will automatically split.


IFFTe-50N-208V-277V-1PH Unavailable

Until further notice, IFFTe-50N-208V-277V-1PH is currently unavailable.


Speed Control (SCR-10/SCR-15)

Please be advised due to supplier challenges, our SCR-10/SCR-15 Vari-speed control is being replaced by another brand. The ratings and the function of the switches are the same. However, the new switch does not have a ground wire. It uses the body of the switch to ground the box it is placed. The new switch does require a screwdriver to adjust speed.